3 July 2018

Special Project: Birth of Voronovytske GCS. New capacities (Part IV)

to the news

Elevatorist.com visited Voronovytske Grain-Collecting Station on 20 June. The elevator is actively preparing for the beginning of new season. A part of construction works is already completed, another part will be finished soon.

All the works are performed as scheduled and by 20 July Voronovytske Grain-Collecting Station will have been commissioned including site improvements done – the road around new silo bins and fire lane, —  Oleksiy Tsurkan, Director of Grain Elevators Division of Alebor noted.

In this issue you will learn about:

Completion of operational silo bins’ mounting;

Flat-bottom silo bins’ construction;

Mounting of grain dryer.

Operational silos’ mounting at Voronovytske Grain-Collecting Station is fully completed. 4 silo bins of KMZ Indusrties production with storage capacity of 1.5 thousand tons each are installed.

Transportation system of KMZ Industries production is assembled over operational bins. Upper chain and lower belt conveyors with capacity 175 tons per hour are installed.

For more details please read the article on elevatorist.com.

other news:

28 December

Roadmap of combine harvesters fleet for 2018

news image
3 September

Special Project: Birth of Chesne GCS. New capacities (Part V)

news image
3 September

Special Project: Birth of Khrystynivske GCS. New capacities (Part V)

news image
3 September

Special Project: Birth of Voronovytske GCS. New capacities (Part V)

news image
3 July

Special Project: Birth of Chesne GCS. New capacities (Part IV)

news image
3 July

Special Project: Birth of Khrystynivske GCS. New capacities (Part IV)

news image
24 May

Special Project: Birth of Chesne GCS. New capacities (Part III)

news image
24 May

Special Project: Birth of Khrystynivske GCS. New capacities (Part III)

news image
24 May

Special Project: Birth of Voronovytske GCS. New capacities (Part III)

news image